Glossary
Glossary of industrial RFQ and tender terms
The terms your team meets in every RFQ and tender package, defined in plain words, with examples from industrial bids.
- Assumption
An assumption is a condition the supplier's offer relies on where the tender package says nothing, stated in writing in the offer. Examples: access to site, utilities, the edition of a standard, or the buyer's review time for drawings. A stated assumption sets the basis of the price, but binds the buyer only once it is accepted in the contract.
- Bid / no-bid decision
A bid / no-bid decision is a supplier's recorded choice on whether to answer an RFQ or tender. It weighs technical fit, commercial terms, capacity, the chance of winning and the cost of preparing the offer. It is usually taken in stages, from the first read of the package or earlier, and reviewed when deviations or terms turn out worse.
- Clarification
In a tender, a clarification is a written exchange that settles what a requirement means. Before the deadline, the supplier asks the buyer about an unclear or contradictory point. After submission, the buyer may ask the supplier to clarify its bid. In public tenders, a clarification after submission cannot change the price or the substance of the offer.
- Compliance matrix
A compliance matrix is a table that lists every requirement in a tender package, one per row, with the supplier's response and a reference to where the offer shows it. Buyers use it to check that nothing was skipped. Suppliers use it to check that nothing was missed before pricing. Each line marked compliant is a commitment.
- Exclusion
An exclusion is part of the scope that the supplier's offer does not include, stated in writing. Typical exclusions are installation, civil works, work beyond the terminal points and third-party inspection fees. When the tender asks for the excluded scope, the exclusion is a departure from the tender, and the buyer evaluates it as one.
- Order of precedence
An order of precedence clause ranks the documents that form a tender or contract, so that when two of them conflict, the higher-ranked one prevails. It decides between documents, not within one. It does not make the prevailing requirement technically right, and some contracts add or substitute a rule that the more stringent requirement applies.
- Pressure class
A pressure class is a dimensionless designation, such as Class 150, 300 or 600, that sets the pressure-temperature rating of flanges and valves under ASME B16.5 and ASME B16.34, and the flange dimensions. The allowable pressure depends on the class, the material group and the temperature. "ANSI 300" is an older name for Class 300.
- Technical bid evaluation
A technical bid evaluation (TBE) is the buyer's check of each offer against the technical requirements of a tender, requirement by requirement. The buyer's engineers review compliance, deviations and missing information, raise technical queries, and assess each offer against the buyer's criteria. In many procedures, only technically acceptable offers go on to the commercial evaluation.
- Technical deviation
A technical deviation is a point where a supplier's offer does not meet the buyer's technical specification. In a bid, the supplier declares it in writing, usually in a technical deviation list, so the buyer can evaluate it. A deviation binds the buyer only once the buyer accepts it and it is written into the contract.
- Technical query (TQ)
A technical query (TQ) is a formal, numbered request for clarification or a technical decision on project requirements, specifications, drawings or other engineering documents. It is exchanged between project parties, during the bid evaluation or after award, tracked in a TQ register and closed once an authorised response is issued. A TQ answer does not by itself change the contract.