Technical query (TQ)
Loonar · Updated 12 November 2026
A technical query (TQ) is a formal, numbered request for clarification or a technical decision on project requirements, specifications, drawings or other engineering documents. It is exchanged between project parties, during the bid evaluation or after award, tracked in a TQ register and closed once an authorised response is issued. A TQ answer does not by itself change the contract.
Also called: TQ, technical clarification request, vendor query.
Technical queries at bid stage
During the technical bid evaluation, the buyer's engineers send each bidder a list of technical queries: missing documents, unclear answers in the compliance matrix, deviations they need explained. On large packages the TQs run in several rounds, each answered by a deadline.
A bid-stage TQ response may become part of the offer, or of the later contract documents, depending on the tender rules and how the answers are incorporated. Write it as if it will. Two rules follow:
- Answer what is asked, with a reference to the page of the offer that supports it.
- Do not use an answer to add a new deviation. In public tenders, an answer may not change the price or the substance of the bid; under World Bank rules, clarifications the buyer did not ask for are not considered (World Bank, ITB 27).
Before the bid deadline, a bidder's own questions to the buyer are usually called requests for clarification. Some buyers call them TQs too. Follow the buyer's wording.
Technical queries after award
After the order, the supplier raises TQs while it engineers and builds the equipment. On EPC projects they often go through the EPC contractor's package engineer or document control, not straight to the owner. Typical TQs:
- a dimension, a nozzle load or a connection detail missing from the purchase order documents;
- two documents that conflict, read against the order of precedence;
- a reference to a client standard or an edition the supplier needs to confirm;
- a proposed alternative, such as a substitute material or test method.
A good TQ states the question, the documents behind it, and the supplier's proposed answer. The buyer can then reply "agreed" instead of writing the answer from scratch, and the TQ closes faster.
TQ vs related requests
| Request | When | What it asks for | Changes the contract? |
|---|---|---|---|
| Clarification | Mostly during the tender | What a requirement means | Not normally |
| Technical query (TQ) | Bid evaluation and after award | An answer on a technical point, formally tracked | Not by itself, unless the contract incorporates it |
| Deviation request | After award, before manufacture | Approval to depart from a requirement | Only once formally accepted and incorporated |
| Concession | After manufacture | Acceptance of a product that does not conform | No; it may authorise acceptance of that item only |
| Change request | After award | A change to scope, price or schedule | Yes, once formally approved |
The names vary between contracts and buyers. What does not vary: a TQ answer is the wrong place to agree a departure or a cost.
The TQ register
Projects track TQs in a register, often kept by the EPC contractor's document control: number, subject, originator, date raised, date due, status, and the documents that change as a result. Before delivery, the supplier checks that every TQ is closed and that each answer has reached the drawings, the material requisitions and the inspection and test plan. An open TQ at the factory acceptance test is a dispute waiting to happen.
Objections, and what holds up
"The buyer agreed it in a TQ, so it is approved." Agreed as an answer, not necessarily as a change. If the contract says TQ answers do not change price, schedule or specification, a substitution agreed in a TQ may still need a deviation request.
"TQs slow the project down." Unanswered questions slow it down more. A TQ with a proposed answer and a clear deadline is the fastest route to a decision on record.
"We will decide ourselves and inform the buyer." Then the supplier owns the decision. If the inspector or the buyer reads the requirement differently later, the cost sits with the party that did not ask.
How Loonar helps
Preparing a TQ starts with the exact requirement behind the question. RFQ Analysis extracts the requirements from the package, traces each one to its source page, and puts conflicting statements across documents side by side. Your engineers have the references a precise TQ needs, and the evidence to support it.
Frequently asked questions
What is the difference between a technical query and a clarification?
A clarification is any written exchange that settles what a requirement means, mostly during the tender. A technical query is the formal, numbered form that EPC projects use for technical questions, before and after award, each tracked in a register. Many TQs are clarifications. Some carry proposals, such as a substitution, that need a different procedure.
Can a TQ approve a deviation?
Only if the contract says so. Many contracts state that a TQ answer is not a change and has no effect on price or schedule. A departure from the specification after award usually needs a deviation request or a concession, and a change with cost goes through the change procedure.
Who answers a technical query?
During the bid evaluation, the bidder answers the buyer's TQs. After award, the supplier's TQs are answered by an authorised representative of the responsible party, often routed through the EPC contractor's document control. A discipline engineer may give the technical assessment, but a formal approval follows the project's approval workflow. Answering a TQ is not the same as approving a change.
What does a TQ form contain?
A unique number, the project and purchase order, the document, revision and clause concerned, the question, the originator's proposed answer, the response deadline, the answer, who approved it, and the date it was closed.
Are TQ answers binding?
An approved TQ answer is usually treated as a project record and followed in engineering. Whether it binds the parties contractually depends on the contract. When an answer affects price, delivery or scope, ask for it to be confirmed through the change procedure.