Glossary
Exclusion
Loonar · Updated 4 November 2026
An exclusion is part of the scope that the supplier's offer does not include, stated in writing. Typical exclusions are installation, civil works, work beyond the terminal points and third-party inspection fees. When the tender asks for the excluded scope, the exclusion is a departure from the tender, and the buyer evaluates it as one.
Also called: scope exclusion, exclusion from the scope of supply.
Many offers group them in one section, often called "assumptions, clarifications and exclusions" or "qualifications and exclusions".
Two kinds of exclusion
- The tender does not ask for it. The exclusion only marks the boundary of the supply: "installation not included", when the RFQ asks for supply only. It prevents misunderstandings and carries little risk.
- The tender asks for it. The exclusion is a departure from the requested scope. The buyer evaluates it like a deviation, and it can make the bid non-responsive.
Exclusion vs deviation
| Deviation | Exclusion | |
|---|---|---|
| The item is | Supplied, but differently | Not supplied |
| When the tender asks for it | A departure from the requirement | A departure from the requested scope |
| Example | Forged body instead of cast | Installation at site not included |
| The buyer evaluates | Whether the alternative is acceptable | Who supplies the missing scope, and at what cost |
Common exclusions in industrial offers
- Installation, commissioning and site testing.
- Civil and foundation works.
- Piping, cabling and other work beyond the terminal points or battery limits.
- Third-party inspection fees.
- Permits and local approvals.
- Operating spares, for example two-year spares, quoted separately.
- Training.
Terminal points are where the supply connects to the buyer's scope, often listed or shown on a drawing. On a process plant, battery limits mark the boundary of a unit. Anything beyond them needs a clear owner.
Why exclusions must be explicit
Buyers evaluate the offer against the scope in the package. A part of the scope that the offer leaves out without saying so is a gap the buyer finds at evaluation or later.
Under World Bank rules, a missing item that is not material can be priced into the bid for comparison, using the average price quoted by the other bidders (World Bank, ITB 30). A missing part that is material makes the bid non-responsive, and the bid cannot be made responsive afterwards by correcting it (World Bank, ITB 29).
How to write an exclusion
- Reference the scope item in the package: document, page and clause.
- State what is excluded, in one line.
- Say whether it is available as an option, priced separately.
For example: "Specification, p. 8, cl. 3.4: installation and commissioning at site excluded. Supervision available as an option, priced per day."
How Loonar helps
RFQ Analysis extracts every requirement in the package, each with its page. Deviation Analysis sets out the full scope of supply in one table, item by item. Your team decides what is in and what is out before pricing, and writes the exclusion list from there.
Frequently asked questions
Can an exclusion get a bid rejected?
Yes, when the excluded scope is a material part of what the buyer asked for. Check the tender's rules on partial offers before you exclude.
Is an exclusion accepted once it is in the offer?
No. The buyer can reject it at evaluation. Many contracts also state that the price includes everything needed for a complete and working supply. Unless the exclusion is written into the contract, that clause can bring the excluded scope back to the supplier.
Should excluded scope be offered as an option?
When you can supply it, yes. It keeps the offer comparable and leaves the choice to the buyer. Check whether the tender evaluates options, or treats them as alternative bids.
What is the difference between an exclusion and an assumption?
An exclusion removes scope from the offer. An assumption states a condition the offer relies on where the package is silent.