Assumption
Loonar · Updated 4 November 2026
An assumption is a condition the supplier's offer relies on where the tender package says nothing, stated in writing in the offer. Examples: access to site, utilities, the edition of a standard, or the buyer's review time for drawings. A stated assumption sets the basis of the price, but binds the buyer only once it is accepted in the contract.
Also called: bid assumption, offer assumption.
Assumption vs clarification vs deviation
- The package says nothing: state an assumption.
- The package is unclear: ask for a clarification. If no answer arrives before the deadline, state the basis of your offer.
- The package is clear and you do not meet it: declare a technical deviation. An assumption that contradicts a stated requirement is a deviation, whatever it is called.
Typical assumptions in industrial offers
| Topic | Example assumption |
|---|---|
| Schedule | Delivery time runs from the buyer's approval of the drawings |
| Document review | Buyer comments on drawings within 10 working days |
| Standards | Editions of the standards in force at the bid date |
| Site | Lifting equipment and utilities at site provided by the buyer |
| Packing | Packing for road transport; seaworthy export packing not required |
Each one applies only where the package is silent. If the RFQ states a review time or a packing standard, that requirement applies, and a different figure is a deviation.
How to write assumptions that hold
- Make each one specific and checkable: a number, a date, a document.
- Say where the package is silent: "not stated in the specification".
- Tie it to what changes if it fails: price, delivery or performance.
- Keep the list short. A long list of general assumptions reads as a limit on the whole offer.
That last point matters at evaluation. The World Bank calls a "reservation" the setting of limiting conditions on the requirements of the tender, and a material reservation makes a bid non-responsive (World Bank, ITB 28 and 29).
How Loonar helps
RFQ Analysis extracts what the package states, each requirement with its page, and flags documents the package refers to but does not include. In Deviation Analysis, parameters the package leaves unstated stay visible in the scope of supply table. Your team writes the assumptions from there.
Frequently asked questions
Is an assumption binding on the buyer?
Only when the buyer accepts it and it is written into the contract or purchase order, for example in an agreed list of deviations and clarifications. Until then it is the basis of your price, not an agreed term.
What is the difference between an assumption and a reservation?
An assumption fills a gap in the package. A reservation limits acceptance of a requirement the package does state. An assumption written as a condition on the offer can be read as a reservation.
Where do assumptions go in the offer?
In a dedicated list, next to the deviations and exclusions, each with its source reference. When the tender includes a form, use the form.
Should I ask a clarification instead of making an assumption?
When the point affects price or delivery and there is time before the deadline for questions, yes. State the assumption as well, so the offer has a clear basis if no answer comes.