In a tender, a clarification is a written exchange that settles what a requirement means. Before the deadline, the supplier asks the buyer about an unclear or contradictory point. After submission, the buyer may ask the supplier to clarify its bid. In public tenders, a clarification after submission cannot change the price or the substance of the offer.
Also called: request for clarification, pre-bid query, bid clarification.
Clarification before submission
The supplier writes to the buyer, within the period the tender sets for questions. That period often closes days before the bid deadline.
Under World Bank rules, the buyer answers in writing and sends the answer to all bidders, without naming who asked. If the answer changes essential elements of the tender, the buyer issues an addendum (World Bank, ITB 7).
Before writing, check the tender's order of precedence clause. It often states which document prevails when two of them conflict, and may answer the question already.
Clarification after submission
During evaluation, the buyer may ask a bidder to clarify its bid. Under World Bank rules, clarifications the buyer did not ask for are not considered. No change to the price or the substance of the bid is allowed, except to confirm the correction of arithmetic errors, and a bid can be rejected if the answer arrives late (World Bank, ITB 27).
Private buyers often hold technical clarification meetings with each bidder after submission. Those can lead to a revised offer. The rules come from the buyer's instructions, not from a general standard. On EPC projects, the buyer's questions often arrive as numbered technical queries (TQs), answered by a deadline and tracked in a register.
Clarification vs deviation vs assumption
| The package | You raise | Example |
|---|---|---|
| Is unclear or contradictory | A clarification | Datasheet says 316L, general specification says duplex |
| Is clear, and you do not meet it | A technical deviation | Forged body offered where a cast body is specified |
| Says nothing | An assumption | Lifting equipment at site not mentioned |
How to write a clarification request
Quote the source, state the conflict, and ask a closed question. Then say what your offer will be based on if no answer comes:
Datasheet DS-101, p. 2, item 7, specifies body material 316L. General specification GS-02, clause 5.3, requires duplex stainless steel for seawater service. Please confirm which applies. Unless instructed otherwise, our offer will be based on duplex, as the more stringent requirement.
Basing the offer on the more stringent requirement keeps it compliant if no answer comes. Basing it on the cheaper reading is a risk the supplier takes, and the buyer may treat it as a deviation.
The more stringent requirement is not automatically the right one. When the two readings lead to a different design, material or interface, such as two pressure classes with different flange dimensions, check that the stricter option still fits the plant, and state in the offer which reading you used and why.
How Loonar helps
RFQ Analysis cross-checks the documents in the package against each other. When two of them conflict, it puts both statements side by side with the page each one came from. Your team decides which one governs, or raises it with the buyer as a clarification.
Frequently asked questions
What is the difference between a clarification and a deviation?
A clarification asks what a requirement means. A deviation states that the offer will not meet a requirement whose meaning is clear. If the answer to a clarification confirms the stricter reading and the offer does not meet it, the point becomes a deviation and must be declared.
Is the buyer's answer to a clarification binding?
When the buyer issues it as an addendum, it becomes part of the tender documents. An answer by email or phone may not be. Ask for it in writing, and check that it is carried into the contract.
Are clarification questions shared with other bidders?
In public tenders, usually yes, without naming who asked. Private buyers set their own rules.
What if the deadline for questions has passed?
Decide the basis of your offer and state it, with the source reference. Many bid teams price the more stringent requirement. A stated interpretation that departs from a requirement can be read as a deviation or a reservation, so use it with care in public tenders.
Is a clarification the same as a technical query (TQ)?
Not quite. A clarification settles what a requirement means, mostly during the tender. A technical query is the formal, numbered form many EPC projects use for technical questions, tracked in a register during the bid evaluation and after the order. At tender stage, many TQs are clarifications.